One and all
You are receiving this email as Facilities Services has you listed as a building manager in a building that will be impacted by our temporary steam shutdown. As part of a necessary safety repair on a leaking steam expansion coupler in the University’s Benton Way tunnel, staff will need to isolate this portion of the system to make repairs in a safe and prudent manner. The anticipated buildings to experience heating loss and hot water loss are as follows:
· Kerr Administration Building,
· McAlexander Field House,
· Shops Buildings,
· Cascade Hall,
· Adams Hall,
· Snell Hall/MU East,
· Bloss Hall
· Arnold Hall,
· Finley Hall
· Hasell Hall.
The follow are buildings we can back feed from alternate directions and maintain service:
· Dixon Rec,
· Gill Coliseum,
· Goss Stadium.
The duration of the work and shutdown is be planned to start at 6:00 AM, August 15th and extend to 5:00 PM, August 16th. If you can forward this information to your respective building staff for input, it would be greatly appreciated. Please let us know if the loss of heat and hot water to your respective will pose an unmanageable hardship. I am happy to walk and talk thru the work with you if desired. Feel free to contact me. Our Work Control Center will be issuing a more general notice as work draws nearer next week.
Zach Golik | Manager | Campus Operations
Facilities| Landscape | Hardscape |Steam | Plumbing
560 SW 15th Street | Corvallis, OR 97331 | Phone: 541-737-5569 | Fax: 541-737-3757 Zach.Golik@oregonstate.edu | http://oregonstate.edu/facilities/